Update – September 26, 2008

September 26, 2008 by garyolson

 

Okay – we haven’t stopped working on building this house.  But we have been busy and it’s been awhile since an update.  We have now had several inspections (gas piping, electrical, framing) which have been passed and allow us to insulate.  That is being done right now.  Hopefully, a framing correction can be quickly completed and we will get approval to cover (install sheetrock).  Once that is done, we can paint, then do floor coverings, cabinets, etc, etc.

On the picture front, how would you like to call your boss and say, please send out a tow truck – ah, better make that two.

Update – September 10, 2008

September 11, 2008 by garyolson

Things have been going on, even if not as obvious.  The front Porch is on and will be roofed soon.  The fireplace framing is done in the great room and the rec room, and the rough in heating and air conditioning is almost done (thank you Lee).

Update – August 24, 2008

August 25, 2008 by garyolson



This past week saw several things accomplished. In addition to the continued work on the heating and air conditioning, we also got the black pipe Natural gas work done, and the piping for the central vacuum. This evening, we had a “Blessing Party”, where our church came out to our house, and wrote on the floors and walls, verses or encouragement. We also enjoyed food and singing. It has been a very wet August, and we are very ready to have skylights installed and remove the drips. Hopefully in the next week, the porch will be installed, and then we can get the roofers back to finish the porch roof and install the skylights.

Update – August 19, 2008

August 20, 2008 by garyolson

I had a little helper to “pound” nails with one day, and am very thankful Bro Lee could come up and mastermind the Heating and AC setup. We ended up with a 3 ton 95% efficiency furnace for the main floor and the basement, and a 2 ton 80% furnace with Heat Pump for the Loft. I also ended up with a sore thumb and lot’s of stories!!!

The gas piping guys arrived yesterday, and promptly slid off the driveway. I will have to post an additional picture of that. We are still waiting for the last posts for the porch, and then siding can go up. We are ready to order cabinets, countertops, interior doors, etc. Hopefully framing inspection will be soon, and then insulation and drywall to follow.

Update – August 10, 2008

August 11, 2008 by garyolson



I have a garage again!!! The garage door was installed on Thursday, and we got a load of tongue and groove pine for the ceiling. The kids helped me (Angela was crowned as Benite Queen), and we got about 3/4 of it conditioned, prior to putting stain on it. The electrician just has a day or two of rough in left, and Lee is coming up tomorrow to start work on the heating and AC duct work. If all goes well, we will be ready for sheetrock in 2-3 weeks. I will probably just publish once a week for awhile as the changes will be less obvious.

Deck Stuff – August 2, 2008

August 3, 2008 by garyolson





Simon and I worked on getting the plywood on the front deck today. We are planning to have it sprayed with a fast setting product from Rhino Liner (think Pickup beds). Gaylen and Katrina really did a nice job of cleaning up after the framers, electricians, and plumbers, all of whom are better at making messes than cleaning them up. As long as we continue to get good framing, plumbing and electrical word done, we won’t complain.

Windows Installed – August 1, 2008

August 2, 2008 by garyolson







Windows were installed yesterday after great effort by the Framing crew. Several of them were in the 35-40 square feet range and being installed high. We only forgot to order one window (above the front door), and it will be here before the porch is finished. We’ve starting cleaning up the framing/plumbing/electrical messes, in anticipation of more messes in our future!!!!

Plumbing/Electrical/Windows – July 31, 2008

July 31, 2008 by garyolson

Rough In Plumbing is almost done, Rough In electrical is moving along, and the windows were delivered yesterday.

Odds & Ends – July 25, 2008

July 27, 2008 by garyolson

The framers have very little left to finish up. The front porch is yet to come and a landing for the deck stairs are a couple of things. It looks like the sheeting is complete and they are ready for a sheer inspection. The plumbers have most of the rough plumbing in. I put some insulation behind the shower areas so that they can finish the rough plumbing of them. Thanks to Lee who lined out the heating and AC plan (while providing much entertainment). The electrician is expecting to start on Monday. Windows are supposed to be delivered on Wednesday, and perhaps installed yet next week. The garage door is on order and we are expecting to have temporary doors for the front, so we are close to a lockable shell.

Stairs In – Decks Up – July 23, 2008

July 24, 2008 by garyolson





The treads for the stairs to the loft were set today (we got a bad board and are waiting for the replacement to finish the last two). Rough in plumbing continued. The big deck was mostly framed.